Sabic Ole 6 Shutdown, Wilton
Project Details:
Emergency repairs to the cooling tower at Ole 6, carried out under 24hr working shutdown conditions.
Work involved cutting and breaking out some of the internal columns and walkways. Temporary structural support was installed before any demolition works commenced.
New reinforced concrete columns were cast in high strength, fast setting concrete, then interconnecting walkways, which had been cast on site previously, and lifted and grouted into position.
Tolent's work scope was completed ahead of schedule which allowed the client to bring the cooling tower back into operation earlier than anticipated.
Contract Details:
Client: Sabic
Architect: Foster Wheeler
Value: £100,000