Seacroft Hospital Newsam Centre

Project Details

This turn key project which included the full refurbishment and fit out of existing consulting rooms into an 18 bedroom and 2 bedroom ward within a live environment. Works included demolition, new toilets and bathrooms, new carpets, new decorations and procurement and installation of fixed and none fixed furniture.

Pre-arranged weekly meetings were held with the hospital manager and daily communications with adjoining wards and facility management team.

As the building we were working in was a mental health wing we based the site set up on the ward we were working on so that we were able to keep a low profile and be as self contained as possible. We kept signage to a minimum whilst still maintaining the requirements for health and safety. As there were service users (patients) both above and below the ward we also kept working hours between 8am and 6pm with very noisy activities not starting until 9am.

Working in a mental health wing we only allowed operatives on site that were CRB checked. No tools were left unattended which if found by a service user could pose a risk to them selves and others.

Tolent followed stringent quality control procedures to ensure that the quality of workmanship on the project was to the highest standards

Contract Details

Client: Equitix Limited

Project: Seacroft Hospital Newsam Centre - Refurbishment & Alteration

Value: £654,616

Search Similar Projects:

Share on Twitter
Please reload

Search By Category

Time Office - Stanley Harrison House

New Ludgate, Mizuho International

Shaftesbury Avenue

The Brasserie, Hudson Quay

1/4
Please reload

Metrovick House

Victoria Halls, Byron Street

The Edge, Westfield Road, Leeds

Reaseheath College

1/3
Please reload

"The Cracker" - Olefins 6 facility, Wilton

Tees Valley Energy From Waste (TV1 & TV2)

Chilton Biomass CCHP Plant

Chilton Foundations

1/2
Please reload

Yarm Medical Centre

Tinshill Medical Centre

Billingham Medical Centre

Linthorpe Medical Centre

1/2
Please reload

Bridon Rope Facility

Trax Park, Doncaster

FHP Factory Unit, Neptune Yard, Walker

Lymedale Distribution Centre, Newcastle under Lyme

1/2
Please reload

Sabic Ole 6 Shutdown, Wilton

Biofuels Corporation Glycerine Plant, Seal Sands

Oikos Storage, Canvey Island, Essex

Polyethylene Plastics Plant, Wilton

1/1
Please reload

Fast Food Outlet, Leeds City Centre

Sports Direct, Ferensway, Hull

Travelodge and Costa Coffee, York

Halbeath Retail Park

1/2
Please reload

Collins Theatre & Apartments, London

Castletown Regeneration

Leafields Development (Southwick)

Pennywell Phase 1 (Hartley Wood)

1/8
Please reload

Time Office - Stanley Harrison House

New Ludgate, Mizuho International

Shaftesbury Avenue

Metrovick House

1/4
Please reload

Newcastle City Library

Wigan Youth Zone

Blackpool Multi Storey Car Park

Seaham Multi-User Centre

1/2
Please reload

© 2016 Tolent Construction Limited (02450574). All trademarks acknowledged. All rights reserved.

Tolent Construction Limited, Ravensworth House, 5th Avenue Business Park, Team Valley, Gateshead, Tyne & Wear, NE11 0HF

  • Twitter Social Icon
  • LinkedIn Social Icon
Tolent Landscape_edited.jpg
  • Grey LinkedIn Icon
  • Grey Twitter Icon